The H-STEM Building Project Timeline and Milestones include:

2019 — Visioning1, Design Team Selection, Project Kickoff and Information Gathering, Programming2, Conceptual Design, Beginning the Schematic Design

2020 — Finalizing the Schematic Design4

2021 —  Design Development and Construction Documents4

2022-2024 — Construction5,6project timeline and milestones

 

1 Selection of Visioning Consultant

2 Conceptual Cost Estimate

3 DTMB Submission, March 2020

4 Legislative Approval, December 2020

5 Groundbreaking, May 2022

6 Grand Opening, January 2024