H-STEM Building Project

Project Milestones

The H-STEM Building Project Timeline and Milestones include:

2019 — Visioning1, Design Team Selection, Project Kickoff and Information Gathering, Programming2, Conceptual Design, Beginning the Schematic Design

2020 — Finalizing the Schematic Design, Beginning Design Development and Construction Documents4

2021-2023 — Construction5,6

Project Timeline and Milestones
  2019 2020 2021 2022 2023
Visioning March - April 20191                    
Design Team Selection   May - June 2019                  

Project Kickoff and Information Gathering

    July 2019                
Programming       August - September 20192              
Conceptual Design         October - November 2019            
Schematic Design           December 2019 - March 20203          
Design Development and Construction Documents             June 2020 - May 20214      
Construction                 May 2021 - August 20235,6

1 Selection of Visioning Consultant

2 Conceptual Cost Estimate

3 DTMB Submission, March 2020

4 Legislative Approval, June 2020

5 Groundbreaking, May 2021

6 Grand Opening, August 2023