Conceptual Design

Moving Pieces—First Concept

Execution

Existing chemical and chemical engineering labs relocated to new addition as required to create space for KIP, BME, BIO, and HRI Offices

Considerations

  • Cost
  • Quantity of labs
    (most expensive space) in new addition
  • Quantity of 'double moves' (relocate existing space and build new then renovate existing vacated space for new function is an added cost)

Moving Pieces—Second Concept

Execution

Existing chemical and chemical engineering labs and offices relocated to new addition as req

 

 

 

 

 

View the full HED presentation from November 1, 2019.