Project Milestones

The H-STEM Building Project Timeline and Milestones include:

2019

  • Visioning1
  • Design Team Selection
  • Project Kickoff and Information Gathering
  • Programming2
  • Conceptual Design
  • Beginning the Schematic Design

2020

Finalizing the Schematic Design4

2021

Design Development and Construction Documents4

2022–2024

Construction5,6

Project Timeline and Milestones
  2019 2020 2021 2022 2023 2024
Visioning March–April1          
Design Team Selection May–June          
Project Kickoff and Information Gathering July          
Programming August–September2          
Conceptual Design October–November          
Schematic Design December 2019–March 20203        
Pandemic Hold   March–December        
Design Development and Construction Documents     January–November4      
Final State and Board of Trustees Approval for Construction     December 2021–January 2022    
Bidding, Mobilization, and Material Procurement       January–April    
Construction       May 2022–March 20245, 6

1 Selection of Visioning Consultant

2 Conceptual Cost Estimate

3 DTMB Submission, March 2020

4 Legislative Approval, December 2020

Groundbreaking, April 2022 with construction beginning May 2, 2022