Active Construction Projects

Planning & Construction provides high-quality master planning, designing, and construction management services. We meet the project's scope, schedule, and budget for new and existing building construction, utility infrastructure, site improvements, renovations, furnishings, and equipment while consistently exemplifying the university's core values.

Below is a list of current active projects with a project budget over $50,000. These projects are in construction or are getting ready to start construction.

If you have any questions, please feel free to contact us at 7-2303. To initiate a project for your department, please submit a Capital Project Request Form.


HSTEM Exterior

Completed Project - Exterior

HSTEM Interior - Completed Project

Completed Project - Interior

HSTEM Lab - Completed Project

Completed Project - Lab

HSTEM Hallway Stairway - Completed Project

Completed Project - Hallway/Stairway

HSTEM Interior - Completed Project

Completed Project - Interior

HSTEM Lab Space

2-1-2024 Lab Space

HSTEM Interior Space

2-1-2024 Interior

Work in Progress (Interior)

2-1-2024 Work in Progress (Interior)

HSTEM Work in Progress January 2024

1-3-2024 Work in Progress

HSTEMM Interior Office Work in Progress

1-3-2024 Office with Furiture

12-1-2023 Work in Progress

12-1-2023 Work in Progress

12-1-2023 Work in Progress

12-1-2023 Work in Progress

12-1-2023 Work in Progress

12-1-2023 Work in Progress

HSTEM Work in Progress - Research Lab

11/1/2023 - Work in Progress - Research Lab

HSTEM  Work in Progress

11/1/2023 - Work in Progress - Office

HSTEM Building - Interior work in progress 9/23/2023

9/29/2023 - Work in Progress - Interior

HSTEM Building work in progress 9/23/2023

9/29/2023 - Work in Progress

HSTEM Work in Progress

8/31/2023 - Work In Progress - 2nd Floor Interior

Hstem Work in Progress 8-28-2023

8/31/2023 - Work in Progress

HSTEM work in progress 8-1-2023

8/1/2023 - Work in Progress

HSTEM work in progress 8-1-2023

8/1/2023 - Work in Progress

HSTEM Interior June 2023

6/30/2023 - Interior Work in Progress

HSTEM Exterior June 2023

6/30/2023 - Exterior Work in Progress

HSTEM Work in Progress Wall Panels 5-31-2023

5/31/2023 - Close-up of Wall Panels

HSTEM Work in Progress 5-31-2023

5/31/2023 - Work in Progress

HSTEM Work in Progress 4-27

4/27/2023 - Work in Progress

HSTEM Work in Progress

4/1/2023 - Work in Progress

HSTEM Work in Progress

4/1/2023 - Work in Progress

HSTEM Work in Progress (interior) 3-1-2023

3/1/2023 - Work in Progress (Interior)

HSTEM Work in Progress 3-1-2023

3/1/2023 - Work in Progress 

2-1-2023 Interior Work in Progress H-STEM Complex

2/1/2023 - Work in Progress (Interior)

1-31-2023 Work in Progress on HStem Complex

1/31/2023 - Work in Progress

1-2-2023 Work in Progress

1/2/2023 - Work in Progress

Work in progress 11/28/2022

11/28/2022 - Work in Progress

work in progress 11/28/2022

1`1/28/2022 - Work in Progress

H-STEM Work in Progress steel framing for walls

10/31/2022 - Work in Progress

9-1-2022 Work in Progress

9/1/2022 - Work in Progress

HSTEM Work in Progress 7-28-2022

7/28/2022 - Work in Progress

Hstem work in progress june

6/29/2022 - Work in Progress

H-Stem work in progress

5/31/2022 - Work in Progress

H-Stem work in progress

5/11/2022 - Work in Progress

H-STEM Engineering and Health Sciences Complex

Before

H-STEM Engineering and Health Sciences Complex

Before

H-STEM Engineering and Health Sciences Complex

Start Date: May 2, 2022

Expected Completion Date: February 2024

Project Description: The H-STEM Complex is a 3-story building addition on the east side of the Chemical Sciences and Engineering building. It will include newly constructed shared and flexible laboratory spaces co-located with renovated classrooms and learning spaces within the existing building. H-STEM Complex will permit teams of researchers and students from the University's various engineering and health sciences departments to work together in collaborative spaces with shared equipment. The H-STEM webpage has more information.


7th street parking lot construction

Work in Progress

7th street parking lot construction

Work in Progress

7th tsreet parking lot construction

Work in Progress

7th Street parking lot rendering

Rendering

 

7th Street Parking Lot

Start Date: September 25, 2023

Expected Completion Date: May 2024

Project Description: New parking lot to replace parking lost to other campus projects. For full details, visit the dedicated webpage for the 7th Street Parking Lot.


Dow Elevator Work in Progress 2-2024

Work in Progress - February 2024

Dow Elevator Addition Work in Progress

Work in Progress - January 2024

Dow Elevator Addition Work in Progress

Work in Progress - January 2024

Dow Elevator Addition Work in Progress - November 2023

Work in Progress - November 2023

Dow Elevator Addition Work in Progress - November 2023

Work in Progress - November 2023

Dow Elevator - Work in Progress

Work in Progress - October 2023

Dow Elevator Work in Progress

Work in Progress - October 2023

Dow Elevator Work in Progress 9/29/2023

Work in Progress- September 2023

Dow Elevator Work in Progress 9/29/2023

Work in Progres - September 2023

Dow Elevator Addition - Work In Progress

Work In Progress - August 2023

Dow Elevator Addition - Work In Progress

Work In Progress - August 2023

Dow Elevator Addition - Work In Progress

Work In Progress - August 2023

Dow Elevator Addition - Before

Before

Dow Elevator Addition - Before

Before

Dow Elevator Addition - Before

Before

Dow Elevator Addition

Start Date: April 24, 2023

Expected Completion Date: July 2024

Project Description: The addition of an elevator to the north side of the Dow Environmental Sciences & Engineering building, including necessary renovations to the existing building.


East Hall Work in Progress

Work in Progress - March 2024

East Hall Work in Progress

Work in Progress - February 2024

East Hall Work in Progress January 2024

Work in progress - January 2024

East Hall Rendering

Future Rendering

East Hall 

Start Date:  October 2023

Expected Completion Date: Fall 2025

Project Description: Construction of the University's new residence hall on the east end of campus near the Rozsa Center. East Hall will house more than 500 students and is slated to offer suites with both single and double occupancy bedrooms and semi-private baths.


Rozsa

Before

Rozsa BF Toilet Remodel

Start Date:  April 2024

Expected Completion Date:  June 2024

Project Description:  Addition of public bathrooms and wellness room in the main lobby area with addition of storage space behind the concessions area.


Daniel Height Renovations - Work in Progress

Work in Progress - April

Daniel Heights Renovations Work in Progress

Work in Progress - April

Daniell Heights Renovations Work in Progress

Work in Progress - April

Daniell Heights Renovations - Before

Before

Daniell Heights 1800 Block Improvements

Start Date:  April 8, 2024

Expected Completion Date:  August 2024

Project Description:  Reconstruction of the 1800 block of Daniell Heights including underground utilities, sidewalks, paving, new lighting, and landscaping.


Mcnair Dining Hall / Kitchen Renovations - Before

Before

McNair Dining Hall Remodel

Start Date:  April 22, 2024

Expected Completion Date:  August 16, 2024

Project Description:  Remodel of a majority of the entire upper level kitchen and dining areas, as well as selected lower level rooms, corridors, and storage areas.